Started Limdu: August of 2020
Started IDES process Feb 21
Legal Council: March 2nd 21
Finished all QTC Apts: March
MEB Referral Date: April 19th 21
NMA done: April 20th 21
MEB Certified: April 21st 21
MEB End date: May 6th 21
Submitted to the PEB: May 27th (don't know why my PEBLO held it for 3 weeks she was blaming the Naval Hospital the whole time saying they hadn't signed their portion. But that was a lie because they signed on the 6th)
PEB accepted on MOL: June 11th 21
VA Compensation: Came back at 50% sometime in July
Started IDES process Feb 21
Legal Council: March 2nd 21
Finished all QTC Apts: March
MEB Referral Date: April 19th 21
NMA done: April 20th 21
MEB Certified: April 21st 21
MEB End date: May 6th 21
Submitted to the PEB: May 27th (don't know why my PEBLO held it for 3 weeks she was blaming the Naval Hospital the whole time saying they hadn't signed their portion. But that was a lie because they signed on the 6th)
PEB accepted on MOL: June 11th 21
VA Compensation: Came back at 50% sometime in July